Construction project more than half complete, on budget

Email

The Pequot Lakes School construction project is 60-65 percent complete, the school board learned Monday night, Jan. 14.

And the board learned that to date, the district has used just .37 percent of construction contingency funds, or $82,958.

The board had put aside 3 percent of construction funds to be used as contingency funds.

The board received an update on the gymnasium addition at the high school at Monday’s regular board meeting.